Reading conflict flags
A conflict is any ERP situation that requires a procurement or production action before the phase-in date can be honoured. Redline detects them automatically and explains each one in plain language.
Types of conflicts
Section titled “Types of conflicts”| Conflict type | What it means | Action generated |
|---|---|---|
| Open PO after phase-in date | A purchase order for the old part is scheduled to arrive after the switch date — stock you will not use | Cancel or amend the PO |
| Production order after phase-in date | A production run is planned to consume the old part past the switch date | Update the BOM for that production order, or hold and reschedule |
| Insufficient new part lead time | The new part cannot arrive in time for the calculated phase-in date given its standard lead time | Expedite the new part order, or adjust the phase-in date |
Conflict indicators in the UI
Section titled “Conflict indicators in the UI”Conflicts are shown at two levels:
- Item level — each affected item in the Phase-In tab shows a conflict badge with a count
- Strategy level — the comparison view shows the total conflict count per strategy
An item with no conflicts shows a green status indicator. An item with one or more conflicts shows an amber or red badge depending on severity.
Resolving conflicts
Section titled “Resolving conflicts”You do not need to resolve conflicts before releasing the ECO. The generated action list contains the instructions for each department to resolve them. Releasing the ECO triggers the notifications that start the resolution process.
If you want to reduce conflicts before releasing, reconsider the strategy. The Stop strategy has the most conflicts (write-offs, cancellations). Run-down typically has the fewest because it respects existing commitments.