CCB process explained
The Change Control Board (CCB) is the governance body that approves, rejects, or defers major engineering changes. Redline does not replace your CCB meeting — it gives the board a structured place to record decisions and automatically triggers the next steps.
What the CCB sees
Section titled “What the CCB sees”CCB members (users with the CCB member flag) see ECRs in CCB Review status in their dashboard. Each ECR shows:
- Title, description, and trigger source
- Classification and severity
- Affected items with part numbers
- Attachments (supplier letters, drawings, test reports)
- Preliminary actions already defined
- The full timeline of status changes and edits
The three decisions
Section titled “The three decisions”| Decision | What happens next |
|---|---|
| Approved | An Engineering Change (EC) is auto-created. ECR data, affected items, and preliminary actions carry over. The assigned coordinator owns the EC. |
| Rejected | The ECR creator receives an email with the rejection rationale. They can accept the rejection (archives the ECR) or edit and resubmit. |
| On hold | The ECR is deferred pending resolution of a condition. The creator can resubmit when the condition is met. |
Coordinator vs CCB decisions
Section titled “Coordinator vs CCB decisions”Not all decisions require a CCB meeting:
- Coordinator decisions — the coordinator can approve minor changes and emergencies directly during screening, without escalating to the CCB
- CCB decisions — major changes are escalated to the board. When the CCB approves, they must also assign a coordinator for the resulting EC
The decision_source field tracks whether the decision came from a coordinator or the CCB.
CCB configuration
Section titled “CCB configuration”In Settings, you can control:
- CCB member flag — assign the CCB role to specific users so they see CCB-pending ECRs
- CCB required for minor — when enabled, even minor changes need CCB approval instead of coordinator-only screening
Audit trail
Section titled “Audit trail”Every CCB decision is recorded with:
- Who made the decision
- The decision type (approved / rejected / on hold)
- The rationale text
- The assigned coordinator (for approvals)
- Timestamp
This creates a complete, auditable governance record.